<div dir="auto">Gary,</div><div dir="auto"><br></div><div dir="auto">I would not say they are “obligated” to extend. I would be inclined to ask why no site work has begun and ask for a fairly defined schedule for the infrastructure work.</div><div dir="auto"><br></div><div dir="auto">Since it is under covenant, no lot buyers would be affected by not extending. However, the applicant invested a lot of funding and the Board a lot of time in getting to the point of a Definitive Plan approval. So. if the applicant can give a good reason for not commencing work and provide a clear schedule for proceeding, I would encourage extending the approval.<br clear="all"><br clear="all"><div dir="auto"><div dir="ltr" class="gmail_signature" data-smartmail="gmail_signature"><div dir="ltr">Thank you<div><br></div><div>Richard Harris, AICP</div><div>PDR, LLC</div><div>Planning Consultant</div><div>413-335-5012</div></div></div></div></div><div><br></div><div><br><div class="gmail_quote"><div dir="ltr" class="gmail_attr">On Sat, Feb 3, 2024 at 7:11 AM Harry LaCortiglia via MassPlanners <<a href="mailto:massplanners@masscptc.org">massplanners@masscptc.org</a>> wrote:<br></div><blockquote class="gmail_quote" style="margin:0 0 0 .8ex;border-left:1px #ccc solid;padding-left:1ex"><u></u>

  
    
  
  <div>
    <p><font size="4" face="Times New Roman">Hi Gary,</font></p>
    <p><font size="4" face="Times New Roman">Our standard Subdivision
        Decision language gives the board the option of extending the
        date if construction hasn't begun. (Although it does not
        obligate the Board to do so.)</font></p>
    <p><font size="4" face="Times New Roman">If your zoning hasn't
        changed in the locus of the subdivision, and the applicant asks
        for an extension before the expiration date, you're probably
        saving a great deal of time and expense by extending it as a
        business item. </font></p>
    <p><font size="4" face="Times New Roman">After all, if the applicant
        needs to come in formally and go through the whole Hearing
        process for the same subdivision approval, it's a bit silly to
        not extend the deadline.</font></p>
    <p><font size="4" face="Times New Roman">All of this is just the
        opinion of an old Planning Board Member...and your results may
        vary, be sure to take into consideration the feelings of your
        Building Inspector, and the involvement of the abutters. <br>
      </font></p>
    <font size="4" face="Times New Roman">Best,</font><br>
    <p><font size="4" face="Times New Roman">H. LaCortiglia</font></p></div><div>
    <p><font size="4" face="Times New Roman"><br>
      </font></p>
    <p><font size="4" face="Times New Roman"><br>
      </font></p>
    <div>On 2/2/2024 8:31 AM, Gary Bechtholdt
      via MassPlanners wrote:<br>
    </div>
    <blockquote type="cite">
      
      
      
      <div>
        <p class="MsoNormal">Hello All:<u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal">Perhaps a good Friday questions.<u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal">Have a Definitive Subdivision Plan approval
          /Covenant about to expire (March 2024) -development has yet to
          commence any type of construction.<u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal">Is the Planning Board obligated to grant
          any sort of extension?
          <u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal">Curious to hear from your experiences &
          thoughts concerning this.<u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal">Thanks,<u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal">-Gary  <u></u><u></u></p>
        <p class="MsoNormal"><u></u> <u></u></p>
        <p class="MsoNormal"><span>R. Gary
            Bechtholdt II<u></u><u></u></span></p>
        <p class="MsoNormal"><span>Planning
            & Community Development Director
            <u></u><u></u></span></p>
        <p class="MsoNormal"><span> <u></u><u></u></span></p>
        <p class="MsoNormal"><b><span style="text-transform:uppercase">Northbridge
              Community Planning & Development</span></b><span><u></u><u></u></span></p>
        <p class="MsoNormal"><span>Aldrich
            School -Town Hall Annex, 14 Hill Street<u></u><u></u></span></p>
        <p class="MsoNormal"><span>(508)
            234-2447<u></u><u></u></span></p>
        <p class="MsoNormal"><span> <u></u><u></u></span></p>
        <p class="MsoNormal"><span>Northbridge
            Memorial Town Hall<u></u><u></u></span></p>
        <p class="MsoNormal"><span>7 Main
            Street, Whitinsville, MA 01588<u></u><u></u></span></p>
        <p class="MsoNormal"><span><a href="http://www.northbridgemass.org/" target="_blank"><span style="color:blue">www.northbridgemass.org</span></a>
            <u></u><u></u></span></p>
        <p class="MsoNormal"><span> </span><u></u><u></u></p>
      </div>
      <br>
      <fieldset></fieldset>
    </blockquote>
  </div>

-- <br>
MassPlanners mailing list<br>
<a href="mailto:MassPlanners@masscptc.org" target="_blank">MassPlanners@masscptc.org</a><br>
<a href="http://masscptc.org/mailman/listinfo/massplanners_masscptc.org" rel="noreferrer" target="_blank">http://masscptc.org/mailman/listinfo/massplanners_masscptc.org</a><br>
</blockquote></div></div>